Application of Cost Control Techniques in Construction Projects Delivery

Authors

  • Horsfall Livinus University of East London
  • Dr Sani Reuben Akoh University of Salford

DOI:

https://doi.org/10.47672/ijpm.2606

Abstract

Purpose: This research work deals on the application of cost control techniques in Construction project delivery. The need for the work arose as projects suffer from cost and time overruns due to factors stemming from poor cost control during at the design and execution stages of Construction projects.

Material and Methods: This study adopted an exploratory research design using a structured questionnaire as the primary instrument for data collection. The research was conducted in Rivers State, Nigeria, known for its robust infrastructure development and relevance to the construction sector. The study population comprised public and private contractors, including civil engineers and quantity surveyors. A random sampling technique was employed to select 50 contractors, considering time and financial constraints.

Findings: The analysis of the data obtained from the respondents identified cost control techniques that include schedules, budgeting, inspection, meetings, reports, records, monitoring & evaluations, as the commonly used techniques for cost control.  The study also revealed that most project managers and contractors in Port Harcourt find it difficult in controlling project costs due to problems which include delays by clients to release fund as at when due, indecision, lack of materials and equipment, bad weather, overlapping of activities, unclear and incomplete drawings, making good defective works, and generally failure to control the productivity of resources. Others of paucity were due to theft and vandalism, interference by clients, high labor turnover, and insufficient knowledge on cost control techniques.

Implications to Theory, Practice and Policy : The study therefore recommends proper knowledge and application of cost control techniques, adequate management of the cost control techniques, good site organization and reporting and adequate supervision of Construction projects should be adopted and implemented.

 

Downloads

Download data is not yet available.

References

Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Important causes of delay in public utility projects in Saudi Arabia. Constuction Managemnt and Economics, 647-655 in

AL-MOMANI, A.H.: Construction delay: a quantitative analysis, International Journal of project management, Vol. 18, No. 1, pp. 51-59, 2000.

Chan Daniel w. m. and Kumaraswamy Mohan M., (2002): Compressing construction durations: lessons learned from Hong Kong building projects, International Journal of Project Management, Vol.20, PP. 23.35

Dissanayaka Sunnil M. and Kumaraswamy Mohan M. (1999): Comparing contributors to time and cost performance in building projects, Building and Environment, Vol. 34, PP. 31- 42

Faridi, A. S., & El-Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167–1176.

Iyer K.C. and Jha K.N., (2005): Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management, Vol. 23, PP. 283.295

JouiniSihem Ben Mahmoud, Midler Christophe and Garel Gilles, (2004): Time-tomarket vs. time-to-delivery; managing speed in engineering, Procurement and Construction projects, International Journal of Project Management, Vol.22, PP. 359.367

Kaming, P.F., Olomolaiye, P.O., Holt, G.D. & Harris, F.C. (1997): Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management Economics, 15(1), pp. 83-94.

Kuprenas John A., (2003): Project management actions to improvedesign phase cost performance, Journal of Management in Engineering, Vol. 19, No.1, PP. 25-32

Love Peter E. D., Tse Raymond Y. C. and Edwards David J., (2005): Time-Cost Relationships in Australian Building Construction Projects, Journal of Construction Engineering and Management, Vol. 131, No. 2, PP. 187-194

Odeh, A.M. &Battaineh, H.T. 2002. Causes of construction delay:

Ogunlana, S.O., Promkuntong, K. &Jearkjirm, V. (1996): Construction delays in a fast-growing economy: Comparing Thailand with other countries. International Journal of Project Management, 14(1), pp. 37-45.

Okuwoga Adeyinka A., (1998): Cost. time performance of public sector housing projects in Nigeria, Habital Intl., Vol. 22, No. 4, PP. 389. 395

Pheng Low Sui and Chuan Quek Tai, (2006): Environmental factors and work performance of project managers in the construction industry, International Journal of Project Management, Vol. 24, PP. 24.37

Reichelt Kimberly and Lyneis James, (1999): The dynamic of project Traditional contracts. International Journal of Project Management, 20(1), pp. 67-73.

Walker, D.H.T. 1995. An investigation into construction time

Downloads

Published

2025-01-27

How to Cite

Livinus, H., & Akoh, D. S. R. (2025). Application of Cost Control Techniques in Construction Projects Delivery. International Journal of Project Management, 7(1), 23–45. https://doi.org/10.47672/ijpm.2606

Issue

Section

Articles