An Investigation of Factors Influencing Construction Project Planning in South Sudan’s Public Road Projects

Authors

  • Teng Athian Master Student, Pan African University, Institute of Basics Sciences, Technology and Innovation (PAUSTI), Nairobi, Kenya
  • James Okaka School of Architecture and Building Sciences (SABS), Jomo Kenyatta University of Agriculture and Technology (JKUAT), Nairobi Kenya
  • Titus Kivaa School of Architecture and Building Sciences (SABS), Jomo Kenyatta University of Agriculture and Technology (JKUAT), Nairobi Kenya

DOI:

https://doi.org/10.47672/ijpm.2598

Keywords:

R42-Project Planning, Public Road Projects, South Sudan, Infrastructure Development, Resource Management

Abstract

Purpose: The purpose of this study is to investigate the factors influencing project planning in public road projects in South Sudan. It aims to identify key challenges and opportunities, contributing to the development of more effective planning practices to enhance infrastructure development and support economic growth.

Materials and Methods: A descriptive research design was employed, incorporating both qualitative and quantitative approaches. Primary data were collected through structured questionnaires targeting professionals in public road projects across South Sudan. Secondary data were gathered from existing literature and official reports. Data analysis utilized the Relative Importance Index (RII) to rank factors influencing project planning.

Findings: The study identifies intergovernmental factors, resource availability, technological infrastructure, and project-specific characteristics as critical determinants of project planning adequacy. It reveals significant gaps in defining project objectives, realistic scheduling, cost estimation, and risk management. The findings underscore the need for enhanced intergovernmental coordination, investment in skilled labor, and adoption of advanced project management tools to address planning deficiencies.

Implications to Theory, Practice and Policy: The research builds on institutional and contingency theories, highlighting the interplay of environmental, organizational, and contextual factors in planning outcomes. For practitioners, it provides actionable insights to improve project planning practices. For policymakers, the study recommends strengthening governance frameworks, standardizing processes, and fostering transparency in planning and implementation.

Downloads

Download data is not yet available.

References

Aali-Bujari, A., & Venegas-Martínez, F. (2021). Impact of Construction Industry on Economic Growth in Africa: Granger Causality and GMM Estimation of Dynamic Panel Models. Review of Economics and Finance, 19, 292–299. https://doi.org/10.55365/1923.X2021.19.30

Africa Development Bank. (2019). Infrastructure Action Plan in South Sudan: A Program for Sustained Strong Economic Growth | African Development Bank Group. https://www.afdb.org/en/countries/east-africa/south-sudan/infrastructure-action-plan-in-south-sudan-a-program-for-sustained-strong-economic-growth

Alan Bryman, E. B. (2016). Business Research Methods. Revista Brasileira de Linguística Aplicada, 5(1), 1689–1699. https://revistas.ufrj.br/index.php/rce/article/download/1659/1508%0Ahttp://hipatiapress.com/hpjournals/index.php/qre/article/view/1348%5Cnhttp://www.tandfonline.com/doi/abs/10.1080/09500799708666915%5Cnhttps://mckinseyonsociety.com/downloads/reports/Educa

Amare, Y., Quezon, E. T., & Busier, M. (2017). Causes of Delays During Construction Phase of Road Projects due to The Failures of Contractor, Consultant, And Employer in Addis Ababa City Road Authority. International Journal of Scientific & Engineering Research, 8(3). http://www.ijser.org

Benedict, O. F. (2018). INFLUENCE OF PROJECT PLANNING ON ROAD CONSTRUCTION PROJECTS PERFORMANCE IN UASIN GISHU COUNTY, KENYA ONDIEK FRANCIS BENEDICT A Research Project Submitted to the Department of Entrepreneurship and Procurement in the School of Human Resource Development in.

Birger, W. (1984). The Resource-Based View of the Firm. Tacit and Ambiguous Resources as Sources of Competitive Advantage, 5(2), 171–180. https://doi.org/10.1057/9781403948083_1

Boulding, K. E. (1956). General Systems Thinking - the skeleton of science. Management Science, 2(3), 197–208. https://doi.org/https://doi.org/10.1287/mnsc.2.3.197

C.R.Kothori. (2016). Research Methodology : Methods and Techniques (Second Revised Edition). In New Age International (P) Limited, Publishers (Vol. 5, Issue 1). https://revistas.ufrj.br/index.php/rce/article/download/1659/1508%0Ahttp://hipatiapress.com/hpjournals/index.php/qre/article/view/1348%5Cnhttp://www.tandfonline.com/doi/abs/10.1080/09500799708666915%5Cnhttps://mckinseyonsociety.com/downloads/reports/Educa

Chan, A. P. C., & Chan, A. P. L. (2004). Key performance indicators for measuring construction success. In Benchmarking (Vol. 11, Issue 2). https://doi.org/10.1108/14635770410532624

DiMaggio, P. J., & Powell, W. W. (2000). The iron cage revisited institutional isomorphism and collective rationality in organizational fields. Advances in Strategic Management, 17(2), 143–166. https://doi.org/10.1016/S0742-3322(00)17011-1

Douglas C. North. (1990). A Transaction Cost Theory of Politics. In E. Case (Ed.), Journal of Theoretical Politics (4th ed., Vol. 2, Issue 4, pp. 355–367). SAGE Publications Ltd. https://doi.org/https://doi.org/10.1177/0951692890002004001

Fashina, A. A., Omar, M. A., Sheikh, A. A., & Fakunle, F. F. (2021). Exploring the significant factors that influence delays in construction projects in Hargeisa. Heliyon, 7(4), e06826. https://doi.org/10.1016/j.heliyon.2021.e06826

Fiedler, F. E. (2015). Effectiveness. 619–632.

Gidado, K. (2004). ENHANCING THE PRIME CONTRACTOR ’ S PRE-CONSTRUCTION PLANNING 1 . Introduction Good planning before implementation is a critical requirement for successful delivery of any project . However , there is an indication that there is often an insufficient time and effort for planning construction projects , especially at tender or pre-contract stage . The planning approach or procedure or process used by contractors also vary from company to company and project to project . There seem to be no “ best practice ” or standardised procedure that is capable of improving the accuracy of predictions of project cost and time . “ If everybody involved in a project can work to an agreed set of processes and procedures , the industry will not only be more efficient , but it will be in a much better position to meet the client ’ s business needs and objectives ” ( Process Protocol level 2 ( 1999 )). The changes the construction industry is experiencing in recent years have spirally increased the complexity of construction processes and thus make pre- construction planning at the right amount of detail and at the right time as an essential ingredient for successful delivery of projects . The work described in this paper therefore addresses these issues or problems and proposes a model that integrates project complexity into construction planning . The work is laid out in the paper in five main parts : Parts one and two focused on identifying the deliverables of construction planning and the components of project complexity respectively . Due to the inconsistency of definitions in the industry , with simple things meaning differently to different people , these parts of the paper have gone in great detail , sometimes explaining rather simple procedures . Each part begins with the basic definitions of construction planning and project complexity respectively . The third part of the paper described the development of a working model that integrates construction planning and project complexity . Conceptual models were initially developed , which were then transformed into a practical ‘ real world ’ model called Tabulated Method Statement ( TBS ). The fourth part described two things : ( 1 ) the findings of structured interviews that explored current practice with the aim of collecting views and opinions from practitioners on current policies , methods and procedures used for pre-construction planning ; and ( 2 ) the devel- opment of a Flowcharted Procedure for Pre-constructio…. 5(1), 87–106.

Harold Kerzner. (2015). Project Management (John Wiley (ed.); 7th ed.). John Wiley & Son, Inc, Hoboken, New Jersey.

Jay Barney. (1991). Firm Resources and Sustained Competitive Advantage (pp. 99–120). Journal of Managemnt. https://doi.org/doi/10.1177/014920639101700108

Kalu, C. M., & Rugami, J. M. (2021). Stakeholder Involvement and Infrastructure Projects Implementation at Kenya Ports Authority. International Journal of Business Management, Entrepreneurship and Innovation, 3(1), 78–90. https://doi.org/10.35942/jbmed.v3i1.166

Khanani, R. S., Adugbila, E. J., Martinez, J. A., & Pfeffer, K. (2021). The Impact of Road Infrastructure Development Projects on Local Communities in Peri-Urban Areas: the Case of Kisumu, Kenya and Accra, Ghana. International Journal of Community Well-Being, 4(1), 33–53. https://doi.org/10.1007/s42413-020-00077-4

Lawrence, P., & Jay, W. (2014). Lorsch (1967) Organization and Environment: Managing Differentiation and Integration. … and Environment: Managing Differentiation and …, 13(1), 180–186. http://scholar.google.com/scholar?hl=en&btnG=Search&q=intitle:Organization+and+Environment+:+Managing+Differentiation+and+Integration#1

Ludwig, B. (1968). General System Theory. In Philosophy of Complex Systems. https://doi.org/10.1016/B978-0-444-52076-0.50006-7

Mahe, A. I., & Umar, A. I. (2021). Assessing the Effect of Strategic Planning on the Performance of Construction Projects: Evidence from Nigeria. Journal of Building Construction and Planning Research, 9(4), 30–37. https://doi.org/10.21522/tijmg.2015.09.01.art001

Majumder, S., Majumder, S., & Biswas, D. (2022). Impact of effective construction planning in project performance improvement. Quality and Quantity, 56(4), 2253–2264. https://doi.org/10.1007/s11135-021-01224-5

Mugenda, A., Mugenda, G. (2003). Research Methods: Quantitative and Qualitative Approaches. African Centre for Technology Studies. http://ir-library.ku.ac.ke/handle/123456789/8328

Munns, A. K., & Bjeirmi, B. F. (1996). The role of project management in achieving project success. In International Journal of Project Management (Vol. 14, Issue 2).

Munyoki, S. K. (2016). Factors Influencing Completion of Construction Projects ; a Case of Construction Projects in Nairobi Kenya. In The Strategic Journal of Business & Change Management (Vol. 2, Issue 4 (62)). http://www.researchgate.net/publication/228964010_Improving_materials_management_practices_on_fast-track_construction_projects/file/60b7d52e2980e268c8.pdf%0Ahttps://en.wikipedia.org/wiki/Construction_industry_of_India

Ngong, C. A., Onyejiaku, C., Fonchamnyo, D. C., & Onwumere, J. U. J. (2023). Has bank credit really impacted agricultural productivity in the Central African Economic and Monetary Community? Asian Journal of Economics and Banking, 7(3), 435–453. https://doi.org/10.1108/ajeb-12-2021-0133

Nyakundi, N. N. (2015). Influence of Project Management Processes on Outcomes : Case of Public Sector Infrastructure Projects At Telkom Kenya Limited. 73.

Ofori-Kuragu, J. K., Owusu-Manu, D. G., & Ayarkwa, J. (2016). The case for a construction industry council in Ghana. Journal of Construction in Developing Countries, 21(2), 131–149. https://doi.org/10.21315/jcdc2016.21.2.7

Ofori, I. K., Armah, M. K., Taale, F., & Ofori, P. E. (2021). Addressing The Severity And Intensity Of Poverty In Sub-Saharan Africa: How Relevant Is The Ict And Financial Development Pathway? Heliyon, 7(10), e08156. https://doi.org/10.1016/j.heliyon.2021.e08156

Paul, G. C. (2023). Road Maintenance Challenges: The Greatest Obstacle to Sustainable Development in South Sudan. Journal of Sustainable Social Change, 15(1), 31–41. https://doi.org/10.5590/jssc.2023.15.1.03

PMI. (2013). A guide to the project management body of knowledge (PMBOK® guide). (PMI (ed.); Fifth). PMI.

Rivera, L., Baguec, H., & Yeom, C. (2020). A study on causes of delay in road construction projects across 25 developing countries. Infrastructures, 5(10), 1–16. https://doi.org/10.3390/infrastructures5100084

Scott, W. R. (1995). Institutional theory : Contributing to a theoretical research program. In K. G. Smith & M. A. Hitt (Eds.). Great Minds in Management, 37(2), 460–484.

World Bank. (2020). Development Projects : South Sudan Transport Sector Development - P179918. https://projects.worldbank.org/en/projects-operations/project-detail/P179918

Zarewa, G. A. (2019). Barriers to Effective Stakeholder Management in the Delivery of Multifarious Infrastructure Projects (MIPs). Journal of Engineering, Project, and Production Management, 9(2), 85–96. https://doi.org/10.2478/jeppm-2019-0010