How Does Project Schedule Management Dimension Influence Building Construction Project Performance? Evidence from County Governments in Kenya

Authors

  • Kennedy Barasa Cherwenyi PhD student, Jomo Kentatta University of Agriculture and Technology (JKUAT, Kenya)
  • Prof Greggory Simiyu Namusonge Professor, Jomo Kenyatta University of Agriculture and Technology (JKUAT, Kenya)
  • Dr. Elizabeth Makokha Nambuswa Lecture, Jomo Kenyatta University of Agriculture and Technology (JKUAT, main Campus Juja, Kenya)
  • Dr. Julius Miroga Lecture, Jomo Kenyatta University of Agriculture and Technology (JKUAT, main Campus Juja, Kenya)

DOI:

https://doi.org/10.47672/ijpm.2998

Keywords:

Project Schedule Management, Project Performance, County Government, Building Construction Projects, Project Regulatory Framework, Stakeholder Satisfaction, Benefits Realization, Strategic Performance

Abstract

Purpose: Effective project schedule management is widely recognized as a critical determinant of construction project success. However, the performance of county government building construction projects in Kenya has traditionally been assessed using the "iron triangle" of time, cost, and scope, with limited attention given to post-completion outcomes such as stakeholder satisfaction, benefits realization, and strategic performance. Consequently, many completed public infrastructure projects have failed to deliver their intended socio-economic benefits despite being completed within planned project constraints. This study examined the effect of project schedule management on the performance of county government building construction projects in Kenya, while also assessing the moderating influence of the project regulatory framework.

Materials and Methods: The study was anchored on complexity theory, theory of constraints, and project management competency theory. The study adopted a mixed-methods research design integrating quantitative and qualitative approaches. A census of 200 respondents drawn from selected county government building construction projects was conducted, yielding 189 valid responses (94.5% response rate). Data were collected using structured questionnaires and analyzed using descriptive statistics, Pearson correlation analysis, and regression analysis.

Findings: The findings revealed that project schedule management has a positive and statistically significant effect on the performance of county government building construction projects (β = 0.323, p < 0.001), explaining 12.6% of the variation in project performance (R² = 0.126). Effective activity sequencing, duration estimation, schedule development, and schedule monitoring enhanced stakeholder satisfaction, benefits realization, and strategic performance. The estimated regression model was Y = 3.702 + 0.323X₁. The findings provide evidence that improvements in schedule management are associated with improved performance of county government building construction projects. Furthermore, the project regulatory framework significantly moderated the relationship between project schedule management and project performance (β = 0.292, p = 0.044), demonstrating that compliance with regulatory requirements strengthens the effectiveness of schedule management practices.

Implications to Theory, Practice, and Policy: The study extends the Kenyan public-construction literature by examining schedule management against a broader conception of project performance that incorporates stakeholder satisfaction, benefits realization and strategic performance rather than relying exclusively on the traditional time-cost-scope measures. The findings emphasize the importance of treating scheduling as an integrated project-management capability involving realistic activity sequencing, duration estimation, schedule development and continuous monitoring. The implications of the study are threefold: theoretically, it strengthens the application of Systems Theory to project scheduling; practically, it provides project managers with specific scheduling practices for improving implementation; and from a policy perspective, it supports stronger institutionalization of schedule planning, monitoring, coordination and accountability within county-government construction governance

Downloads

Download data is not yet available.

References

Adetoba, O., & Potluri, R. M. (2025). Project management: The new frontiers of opportunities in Africa with specific country-based case studies. Kazakh-British Technical University.

Amegboleza, A. A., Acakpovi, A., & Ülkü, M. A. (2025). Project management challenges in client-consultant decision-making: A case for the Ghanaian mining construction industry. Canadian Journal of Administrative Sciences / Revue Canadienne des Sciences de l'Administration, 42(2), 302–319. https://doi.org/10.1002/cjas.1772

Andersen, E. S. (1996). Warning: Activity planning is hazardous to your project's health! International Journal of Project Management, 14(2), 89–94. https://doi.org/10.1016/0263-7863(95)00056-9

Aroge, I. O., Osho, A. E., Akinyuwa, B. O., Ajao, A. C., & Sunmola, F. O. (2025). Construction management and sustainability: A bibliometric review of project success factors, challenges and opportunities in South Africa and Nigeria. Open Journal of Engineering Science, 6(1), 15–29. https://doi.org/10.52417/ojes.v6i1.807

Asiedu, R. O., & Adaku, E. (2019). Cost overruns of public sector construction projects: A developing country perspective. International Journal of Managing Projects in Business, 13(1), 66–84. https://doi.org/10.1108/IJMPB-09-2018-0177

Association for Project Management. (2019). APM body of knowledge (7th ed.). Association for Project Management.

Awino, S. O., & Musembi, A. (2024). Cost control measures and performance of dam projects in Kirinyaga County, Kenya. International Research Journal of Business and Strategic Management, 6(2), 261–274.

Basil, B. M., & Waruguru, M. (2024). Cost management practices and performance of Ministry of Education funded school construction projects in Marigat Sub County. International Journal of Social Science and Humanities Research, 2(1), 190–204.

Bello, H. (2020). Re: How many respondents do i need for conducting a pilot study? ResearchGate. https://www.researchgate.net/post/How-many-respondents-do-I-need-for-conducting-a-pilot-study/5e5e10f3a4714bb19d560d81/citation/download

Benegusenga, J. (2022). Total quality management and construction projects in Rwanda: A case illustration of project management practices and performance [Conference paper]. Kigali University.

Bevans, R. (2022, September 19). Types of variables in research and statistics. Scribbr. https://www.scribbr.com/methodology/types-of-variables/

Blomquist, T., Hällgren, M., Nilsson, A., & Söderholm, A. (2010). Project-as-practice: In search of project management research that matters. Project Management Journal, 41(1), 5–16.

Bor, K. E., & Miroga, J. (2024). Project development approaches and performance of constituency development fund construction projects in the County Government of Kakamega, Kenya. Strategic Journal of Business & Change Management, 11(4), 496–510. https://doi.org/10.61426/sjbcm.v11i4.3101

Chepkoech, E. (2016). Factors influencing performance of Uwezo Fund supported projects in Bomet County, Kenya [Master's research project, University of Nairobi].

Chepkemoi Kirui, B., & Gichana, J. O. (2024). Project management practices and sustainability of building projects in Kenya: A case study of construction firms in Nairobi County, Kenya. African Journal of Emerging Issues, 6(7), 75–91.

Chepkwony, A. K., Muchelule, Y. W., & Somba, S. M. (2023). Project cost management and performance of National Housing Corporation projects in Kenya. International Journal of Social Science and Humanities Research, 1(1), 761–771.

Fragidis, L. L., & Chatzoglou, P. D. (2018). Implementation of a nationwide electronic health record (EHR). International Journal of Health Care Quality Assurance, 31(2), 116–130. https://doi.org/10.1108/IJHCQA-09-2016-0136

Cohen, E. (2022). The complete guide to resource planning in project management. Creative Manager Inc. dba Workamajig.

Controller of Budget. (2024). Annual County Governments budget implementation review report for FY 2023/2024.

Controller of Budget. (2025). Annual County Governments budget implementation review report for FY 2024/2025.

Council of Governors. (2017). Performance management framework for County Governments, 2017.

County Government of Busia. (2022). County annual progress report for the financial year 2021/2022. County Treasury and Economic Planning, County Government of Busia. https://www.busiacounty.go.ke/resources/county-treasury/

Creswell, J. W. (2014). Research design: Qualitative, quantitative and mixed methods approaches (4th ed.). Sage.

Ephrem, G. S., Tripathi, K. K., Syed Zafar, S. T., & Kumar, N. J. (2019). Modeling performance factors for public construction projects with the SEM approach: Engineer's perspective. Engineering, Construction and Architectural Management, 26(10), 2410–2431.

Flyvbjerg, B., Buhl, S. L., & Skamris, M. K. (2019). How common are cost overruns in transport infrastructure projects? Transportation Review, 23(1), 71–88.

Gangla, I. S., Kingo'riah, G. K., & Nyagwachi, J. N. (2025). Project management practice and performance of building projects in Kenya: Case of Migori, Homabay and Kisii Counties. International Journal of Innovative Science and Research Technology, 10(9), 1546–1554. https://doi.org/10.38124/ijisrt/25sep449

Gitahi, G. J. (2023). Project scope management and performance of projects: A case of water and sanitation infrastructure projects in Mombasa and Kilifi Counties, Kenya. Kenyatta University.

Government of Kenya. (2010). Constitution of Kenya.

Government of Kenya. (2011). National Construction Authority Act, No. 41 of 2011.

Government of Kenya. (2012). Public Finance Management Act, No. 18 of 2012.

Government of Kenya. (2015). Public Procurement and Asset Disposal Act, No. 33 of 2015.

Government of Kenya. (2022). Public finance management (Public investment management) regulations, 2022.

Government of Kenya. (2025). Annual progress report 2023/2024, Fourth Medium Term Plan (MTP IV).

Government Project Reporting Information System. (2025). Government Project Reporting Information System.

Hatamleh, M. T., Hiyassat, M., Ghaleb, J. S., & Rateb, J. S. (2018). Factors affecting the accuracy of cost estimate: Case of Jordan. Engineering, Construction and Architectural Management, 25(1), 113–131. https://doi.org/10.1108/ECAM-10-2016-0232

Hussin, S., & Omran, L. (2017). Problems of projects and delays in the construction industry of Pakistan. Australian Journal of Business and Management Research, 5(1), 41–50.

Institute of Economic Affairs. (2025). Kenya's stalled projects expose deep flaws in budget planning and execution.

International Organization for Standardization. (2020). ISO 21502:2020: Project, programme and portfolio management—Guidance on project management.

Isaboke, M. E., & Kwasira, J. (2016). Assessment of budgeting process on financial performance of county government of Nakuru Kenya. International Journal of Economics, Commerce and Management, 4(5), 134–150.

Jayarathna, Y. S. M. D., & Weerakkody, W. A. S. (2016). Impact of decision making, reward management on job performance: Mediation of job satisfaction: A case of a private bank in Sri Lanka. European Journal of Business and Management, 8(32), 65–73.

Jobidon, G., Lemieux, P., & Beauregard, R. (2018). Implementation of integrated project implementation in Québec's procurement for public infrastructure: A comparative and relational perspective. Sustainability, 10(8), 2648.

Kajwang, J. O., & Nzulwa, J. (2018). Determinants on performance of county governments projects in Kenya: A case of Homa Bay County.

Kariuki, J., & Mwangangi, P. (2023). Regulatory compliance and performance of county government infrastructure projects in Kenya.

Keseko, E. K., & Tumuti, J. (2025). Project integration management and performance of building construction projects in Nairobi City County, Kenya. Strategic Journal of Business & Change Management, 12(3), 650–670. https://doi.org/10.61426/sjbcm.v12i3.3354

Kibaara, I. M. (2018). Factors influencing the performance of building contractors in infrastructural development in Nakuru County, Kenya [Master's thesis, University of Nairobi].

Kimiti, S. (2018). A critical analysis of the causes of project management failures in Kenya. International Journal of Soft Computing and Engineering, 4(1).

Kinyanjui, P. M., Ngugi, P. K., & Ombui, K. (2022). Project scope definition and performance of government construction projects in Kenya. African Journal of Emerging Issues.

Kipyegon, B. S., Muchelule, Y., & Okello, B. (2025). Project communication and performance of road infrastructure projects in Kenya. Strategic Journal of Business & Change Management, 12(2), 958–979. https://doi.org/10.61426/sjbcm.v12i2.3252

Kirui, L. C., & Gichana, J. O. (2024). Project management practices and sustainability of building projects in Kenya: A case study of construction firms in Nairobi County. African Journal of Emerging Issues, 6(7), 75–91.

Knief, U., & Forstmeier, W. (2018). Violating the normality assumption may be the lesser of two evils. https://doi.org/10.1101/498931

Komal, B., Janjua, U. I., Rehman, M., Nawaz, M., & Arif, M. (2020). The impact of scope creep on project success: An empirical investigation. IEEE Access, 8, 125755–125775. https://doi.org/10.1109/ACCESS.2020.3006981

Kothari, C. R., & Garg, G. (2014). Research methodology: Methods and techniques. New Age International Publishers.

Kyalo, A. M., & Kising'u, T. M. (2024). Project planning practices and performance of road construction projects in Kwale County, Kenya. Strategic Journal of Business & Change Management, 11(1), 823–845.

Lagat, D., Njuguna, M., Kivaa, T., & Mutungi, S. (2025). Assessing the level of regulatory compliance in construction projects in Nairobi City County, Kenya. International Journal of Engineering Trends and Technology, 73(5). https://doi.org/10.14445/22315381/IJETT-V73I5P120

Lampa, I. L., de Godoi Contessoto, A., Amorim, A. R., Zafalon, G. F. D., Valêncio, C. R., & de Souza, R. C. G. (2017). Project scope management: A strategy oriented to the requirements engineering. In Proceedings of the 19th International Conference on Enterprise Information Systems (ICEIS 2017) (Vol. 2, pp. 370–378). SCITEPRESS – Science and Technology Publications. https://doi.org/10.5220/0006318603700378

Love, P. E., Ahiaga-Dagbui, D. D., & Irani, Z. (2016). Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation. Transportation Research Part A: Policy and Practice, 92, 184–194.

Maendo, D. O., James, R., & Kamau, L. (2018). Effect of project monitoring and evaluation on performance of road infrastructure projects constructed by local firms in Kenya. International Journal of Economics, Business and Management Research, 2(4), 317–328. https://ir-library.ku.ac.ke/handle/123456789/18856

Makau, R. M., & Moronge, M. (2018). Determinants of project team performance in building construction projects in Nairobi County, Kenya. Strategic Journal of Business & Change Management, 5(4), 90–108. https://doi.org/10.61426/sjbcm.v5i4.884

Mathenge, P. M. (2020). Project management practices and performance of the public projects in Mombasa County, Kenya [Master's thesis, Kenyatta University]. Kenyatta University Institutional Repository. https://ir-library.ku.ac.ke/items/d45a0422-6922-47b6-85b5-2c5373282ddc

Mogoa, A. M., & Muchelule, Y. (2023). Project schedule management on performance of construction projects in Mombasa County, Kenya. Strategic Journal of Business & Change Management, 10(2), 582–603. https://doi.org/10.61426/sjbcm.v10i2.2624

Monitoring and Evaluation Unit. (2019). Assessment report for Masol Integrated Project, County Government of West Pokot.

Muinde, J. N., Simon, S. M., & Okaka, J. O. (2025). An evaluation of stakeholder management performance in county government-funded construction projects: A case of Machakos County. East African Journal of Engineering, 8(1), 145–161. https://doi.org/10.37284/eaje.8.1.2900

Mwandoro, H. K., & Muchelule, Y. (2024). Project management competencies and performance of building construction projects in Mombasa County. International Journal of Social Sciences Management and Entrepreneurship, 8(1), 995–1006.

Mwangi, W. K., & Omwenga, J. Q. (2025). Scope creep and performance of construction projects in Kiambu County, Kenya.

National Assembly Committee on Public Accounts. (2025). Report on fiduciary risk in county governments, FY 2023/2024.

Nishimwe, J., & Akims, M. A. (2026). Project management capabilities and performance of projects by Fair Construction Limited Kigali, Rwanda. Journal of Entrepreneurship & Project Management, 10(1), 74–92. https://doi.org/10.53819/81018102t2565

Nishimwe, J., & Akims, M. A. (2026). Quality management system implementation and timely completion of building projects: Evidence from Rwanda. Journal of Construction Project Management and Innovation, 16(1).

Njoka, E. M., Simon, S. M., & Okaka, J. O. (2024). Evaluating the managerial performance within construction projects in Kenya. East African Journal of Engineering, 7(1), 339–350.

Ombwayo, J., Kidombo, H., & Gakuu, C. (2026). Moderating influence of stakeholder involvement on the relationship between project management lifecycle and performance of slum upgrading projects: A case of Nairobi City County, Kenya. International Journal of Construction Management, 26(1), 1–11. https://doi.org/10.1080/15623599.2024.2398271

Ombwayo, J., Kidombo, H., & Gakuu, C. (2024). A nexus between project management lifecycle and performance of slums upgrading projects in Nairobi City County, Kenya. Journal of Sustainable Development, 17(4), 88–102.

Office of the Auditor-General. (2024). Summary report of County Governments for the financial year 2023/2024.

Office of the Auditor-General. (2025). Summary report of the Auditor-General on County Governments for the financial year 2023/2024.

Ogunberu, A., Olaposi, K., & Akintelu, K. (2016). Effective management of the triple constraint through polarity management techniques: A refreshed perspective. University of Johannesburg.

Omondi, D., Wanyonyi, L., & Kibet, S. (2024). Public investment management regulations and performance of devolved government projects in Kenya.

Omulupi, P. (2022). Project time scheduling on successful implementation of healthcare projects in Nairobi County. International Journal of Project Planning and Management, 5(2), 41–51.

Oyebowi, L. O., Jimoh, R., Ganiyu, B. O., & Shittu, A. A. (2016). Analysis of causes and impact of variation order on educational building projects. Journal of Facilities Management, 14(2), 139–164. https://doi.org/10.1108/JFM-01-2015-0001

Oyier, M., & Tumuti, J. (2025). Project management and performance of residential construction projects in Nairobi City County, Kenya. Journal of Entrepreneurship & Project Management, 5(1), 19–28. https://doi.org/10.70619/vol5iss1pp19-28

Pinsent Masons. (2016). Collaborative construction: More myth than reality? https://www.pinsentmasons.com/about-us/announcements/pinsent-masons-launches-inaugural-collaborative-construction-report

Pinto, J. K., & Winch, G. (2016). The unsettling of “settled science:” The past and future of the management of projects. International Journal of Project Management, 34(2), 237–245.

Pirozzi, M. (2018). The stakeholder management perspective to increase the success rate of complex projects. PM World Journal, 7(1), 1–12. https://pmworldlibrary.net/article/the-stakeholder-management-perspective-to-increase-the-success-rate-of-complex-projects/

Project Management Institute. (2018). Pulse of the profession® 2018: Success in disruptive times. Project Management Institute. https://www.pmi.org/learning/thought-leadership/pulse/pulse-of-the-profession-2018

Project Management Institute. (2019). Pulse of the profession® 2019: The future of work—Leading the way with PMTQ. Project Management Institute. https://www.pmi.org/learning/thought-leadership/pulse/the-future-of-work-leading-the-way-with-pmtq

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Project Management Institute.

Project Management Institute. (2024). Pulse of the profession® 2024: The future of project work. Project Management Institute.

Republic of Kenya. (2025). State Department for Public Works annual report.

Roseke, B. (2019, February 14). Guide to project communications management. ProjectEngineer. https://www.projectengineer.net/guide-project-communications-management/

Roseke, B. (2019, July 26). The role of the project team. ProjectEngineer. https://www.projectengineer.net/the-role-of-the-project-team/

Roseke, B. (2019). What is the schedule performance index? ProjectEngineer. https://www.projectengineer.net/what-is-the-schedule-performance-index/

Rugenyi, F. (2016). Assessment of the influence of project management competence on the triple constraint in projects in Nairobi. International Journal of Academic Research in Business and Social Sciences, 6(4), 295–309.

Saidu, I., & Shakantu, W. (2017). An investigation into cost overruns for ongoing building projects in Abuja, Nigeria. Acta Structilia, 24(1), 53–72. https://doi.org/10.18820/24150487/as24i1.3

Salykova, L., & Abylova, V. (2019). Critical performance factors in project management. PM World Journal, 8(5).

Samo, T. B., Shale, N. I., & Wairiuko, J. W. (2024). Cost management practices and performance of roads construction projects in Kenya. International Journal of Social Science and Humanities Research, 2(3), 31–45.

Saya, B., & Onyango, J. O. (2024). Project contractors’ capacity and performance of road construction projects in Uasin Gishu County, Kenya. Journal of Entrepreneurship & Project Management, 8(6), 88–112. https://doi.org/10.53819/81018102t2424

Tirimba, W., & Odhiambo, C. (2025). Synchronous scope planning and performance of housing projects by State Department of Housing and Urban Development in Nairobi County, Kenya. Journal of Entrepreneurship & Project Management, 5(1), 19–28.

Wanyonyi, S., & Muturi, W. (2017). Factors influencing completion of county government funded projects in Trans-Nzoia County. International Journal of Management and Commerce Innovations, 4(2), 555–569. https://www.researchpublish.com/papers/factors-influencing-completion-of-county-government-funded-projects-in-trans-nzoia-county

Waweru, Z. W. (2018). Influence of teamwork approach on project performance: A case of road construction in Kericho County, Kenya [Doctoral dissertation, University of Nairobi].

Wei, N. C., Bao, C. P., Yao, S. Y., & Wang, P. S. (2016). Earned value management views on 4D CAD and EVMS. In Computing in Civil Engineering 2005 (pp. 1–8). American Society of Civil Engineers.

Wellingtone. (2020). The state of project management 2020. Wellingtone. https://wellingtone.co.uk/wp-content/uploads/2020/06/The-State-of-Project-Management-Report-2020-Wellingtone.pdf

Zarewa, G. A., Ibrahim, A. D., Ibrahim, Y. M., & Adogbo, K. J. (2018). Governance impact assessment on large infrastructure project (LIP) delivery. Journal of Engineering, Project & Production Management, 8(1).

Downloads

Published

2026-09-22

How to Cite

Cherwenyi, K., Namusonge, G., Nambuswa, E., & Miroga, J. (2026). How Does Project Schedule Management Dimension Influence Building Construction Project Performance? Evidence from County Governments in Kenya. International Journal of Project Management, 8(2), 1 – 26. https://doi.org/10.47672/ijpm.2998